Bella Vista All Weather Track Project Pictures
| Monday, November 12 - First demo of curb and fence | |
![]() |
![]() |
| Just getting started on demolition of inside south curb. | Tearing out fence posts of north fence. |
![]() |
![]() |
| Cleaning up curb near Madison Ave. | More curb demo on north end. |
![]() |
![]() |
| Tearing up the backstretch. | Project manager Clay Taft and Project Foreman Randy Chance (Teichert Inc.) |
![]() |
![]() |
| Taking out the southern most long jump runway. | Grading the temporary discus sector - north end. |
![]() |
![]() |
| Some grading on the backstretch. | Working on the homestretch. |
![]() |
![]() |
| Grading the north turn. | Digging trench for electrical, finish lynx, and microphone cord conduit. |